Export cable route survey, Dogger Bank Wind Farm

High-resolution seismic and side-scan sonar reconnaissance for 65km inter-array and export cable burial pathways in variable shallow till and boulder fields.

Sector: Offshore Wind Duration: 4 weeks Location: North Sea, UK
Export cable route survey, Dogger Bank Wind Farm
SYSTEM SUPPLIED Applied Acoustics CSP-D2400 Seismic System
PROJECT SCOPE & OVERVIEW

About This Campaign

High-resolution seismic and side-scan sonar reconnaissance for 65km inter-array and export cable burial pathways in variable shallow till and boulder fields.

High-resolution seismic and side-scan sonar reconnaissance for 65km inter-array and export cable burial pathways in variable shallow till and boulder fields.

TECHNICAL EXECUTION

Challenge & Delivered Outcome

THE CHALLENGE

Operational & Site Constraints

Harsh sea conditions and erratic boulder fields requiring real-time UXO and obstacle discrimination.

THE OUTCOME

Deliverables & Client Impact

Complete micro-siting corridor chart supplied, saving an estimated 14 days of trenching tool re-routes.

Key Technologies:
Cable route Boulder clearance Subsea survey